YOU'RE LISTENING TO

Red Eye Radio

12:00 AM - 5:00 AM

YOU'RE LISTENING TO

Red Eye Radio

12:00 AM - 5:00 AM

Upcoming road construction schedule for Jackson-Madison County

MADISON COUNTY, I-40: The widening of I-40 east of US 45 (SR 5) MM 82.0 to east of US 70
(SR 1) MM 87.0 in Jackson, including bridges, retaining walls and installation of TDOT Smartway Intelligent Transportation System.

Today through Wednesday August 17, 7 p.m. – 6 a.m.: I-40 east and westbound from MM 82.0 to MM 87.0 will have intermittent left and right lane closures for construction activities. Restrictions: There is an 11’ width restriction east and westbound from MM 82.1-MM 88.5.

LOOK AHEAD: Wednesday, August 17 through Wednesday August 24, 7 p.m. – 6 a.m. – I-40 east and westbound from MM 82.0 to MM 87.0 will have intermittent left and right lane closures for construction activities.

MADISON COUNTY, I-40: The grading, drainage, construction of bridges, retaining walls and noise walls, ITS and paving on I-40 from west of US 412 (SR 20, Hollywood Drive) to west of the US 45 Bypass (SR 186).

Today through Wednesday, August 17, 7 p.m. – 6 a.m. – (AS NEEDED) I-40 east and westbound will have intermittent lane closures from east of MM 76.0 (Exit 76) to east of MM 80.0 for traffic control work and Phase 1 shoulder work.

Thursday, August 11, 7 p.m. – 6 a.m. – The I-40 WB Exit 79 Ramp (to US 412/S.R. 20) will be closed for the removal of the existing overhead sign. A rolling roadblock will be utilized when the existing truss is lifted during the removal. (BACKUP DATE: Friday, August 12, 7 PM-6 AM)

Speed limit reduced to 65 MPH on I-40 eastbound from MM 75.2 to MM 76.9 and 55 MPH from MM 76.9 to MM 79.9. Speed limit will be reduced to 55 MPH I-40 westbound from MM 82.3 to MM 78.4.

LOOK AHEAD: Wednesday, August 17 through Wednesday, August 24, 7 p.m. -6 a.m. – I-40 east and westbound will have intermittent lane closures from east of MM 76.0 (Exit 76) to east of MM 80.0 for traffic control work and Phase 1 shoulder work.

Share On

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top
Monday-Friday
Saturday-Sunday

Deal Of the Day

Thursday

ThursdayGet Deal

Stock Market Brought To You By Talk N West TN

Crypto Brought To You By Mann's Wrecker

    Bitcoin