From the Tennessee Department of Transportation –
Madison County – I-40 – The grading, drainage, construction of bridges, retaining walls and noise walls, ITS and paving on I 40 from west of US 412 (SR 20, Hollywood Drive) to west of the US 45 Bypass (SR 186).
Continuign through Wednesday, September 27, 7 p.m. – 6 a.m. – I-40 east and westbound will have intermittent lane closures from east of MM 76.0 (Exit 76) to east of
MM 80.0 for barrier rail removal, milling, and asphalt work.
LOOK AHEAD: Wednesday, September 27 through Wednesday, October 4, 7 p.m. – 6 a.m. – I-40 east and westbound will have intermittent lane closures from east of MM 76.0 (Exit 76) to east of MM 80.0 for milling and asphalt paving work.
Madison County – I-40 – The grading, drainage and paving with Portland Cement Concrete on I 40 (Exit 93) at the SR 152 (Law Road) interchange.
Continuing through Wednesday, September 27, 7 p.m. – 6 a.m. – I-40 east and westbound from MM 92.0 to MM 94.0 will have intermittent left and right lane closures for construction activities.
LOOK AHEAD: Wednesday, September 27 through Wednesday, October 4, 7 p.m. – 6 a.m. – I-40 east and westbound from MM 92.0 to MM 94.0 will have intermittent left and right lane closures for construction activities.
Madison County US -70 (SR-1) – The resurfacing on US 70 (SR 1) from near Mobile Street to Whitehall Street will cause temporary lane closures in both directions. One lane will remain open at all times. Motorists should watch for crews and equipment in the roadways.
Madison County US-412 (SR-20) – The resurfacing on US 412 (SR 20) (Parkway Ave.) from near I-40 to US 70 (SR 1), including bridge expansion joint repair and thin epoxy overlay will cause temporary lane closures in both directions. One lane will remain open at all times. Motorists should watch for crews and equipment in the roadways.