From the Tennessee Department of Transportation
The Tennessee Department of Transportation will halt all lane closure activity on interstates and state highways for the 4th of July holiday travel period. From 12 noon, Thursday, July 3, to 6 a.m. on Monday, July 7, no lane closures will be allowed.
There will be possible DAYTIME or NIGHTTIME lane closures at various locations in Region 4 to make repairs or new installs on an as needed basis at various locations throughout the 21 counties.
District 47
BENTON COUNTY
I-40 at Exit 126 The grading, drainage, and paving on I-40 at the US-641 (SR-69) interchange (Exit 126) will cause temporary lane closures throughout the project.
BENTON COUNTY
SR-69 The Resurfacing on SR69 from the Decatur County line to James Walker Road will cause temporary lane closures throughout the project.
CARROLL COUNTY
SR-1 The Resurfacing on SR1 (US 70) from near Rutherford Fork Obion River to SR22 includes all directions of Huntingdon Square) will cause temporary nightly and daily lane closures throughout the project for milling and paving.
CARROLL COUNTY
SR-22 The intersection improvements on SR 22 and Clyde Road at the Huntingdon Industrial Park entrance will cause lane closures throughout the project.
SR-22 The intersection improvements on SR 22 and Lexington Street at the Huntingdon Industrial Park entrance serving Dynamix Casting Fluxes will cause lane closures throughout the project.
CARROLL COUNTY
SR-76 (US-79) The grading, drainage, noise walls, signals and paving on U.S. 79 (S.R. 76) from near S.R. 77 to near Cutlip Lane will cause lane closures throughout the project.
Wednesday June 18, 2025 Traffic will be shifted to the new alignment from near Cutlip Lane to the Connector Road leading into Trezevant, speed limit reduced to 35 MPH. Traffic will proceed down new alignment to an All Way Stop and then proceed onto Old US79 (SR76). Weather dependent.
DYER COUNTY
SR-78 The Resurfacing on SR78 from near US 51 (SR3) to SR103 will cause temporary nightly and daily lane closures throughout the project for milling and paving.
GIBSON COUNTY
SR-420 The Resurfacing on SR420 from US 45W (SR 5) to SR 186 will cause temporary lane closures throughout the project.
HENRY COUNTY
SR-218 The Resurfacing on SR218 from SR77 to SR76 will cause temporary lane closures throughout the project.
OBION COUNTY
U.S. 51(SR3) The construction of turn lanes on U.S. 51 (S.R. 3) at Greenfield Drive/N. Morgan Street for State Industrial Access (SIA) support serving Williams Sausage HQ will cause an inside lane closure on U.S. 51(SR3) to thru traffic during construction. The cross-over at Greenfield Drive and N. Morgan Street will also be closed to thru traffic during construction. The Speed Limit is reduced from 50 mph to 40 mph on U.S. 51.
OBION COUNTY
U.S. 51(SR3), U.S. 45 (SR 5) Soil boring work will cause temporary lane closures on U.S 51 and U.S. 45 in South Fulton. This work will take place in the interchange of U.S. 51 and U.S. 45 and areas immediately adjacent to the interchange along these routes.
District 48
CHESTER COUNTY
SR100 between E. Main Street and Baker Road
Crews are replacing 2 bridges on SR100 between E. Main Street and Baker Road. Please use caution throughout the area. There is a temporary traffic signal in place at the bridge over Dry Creek, east of Henderson.
DECATUR COUNTY
SR20 (US 412) From SR69 (LM 3.59) to the Perry Co line (LM 9.14) in Parsons, TN – There will be lane closures daily for resurfacing work including bridge repairs.
HARDEMAN COUNTY
US64 (SR15) from Walton Road to Davis Way through Bolivar, TN – There will be lane closures daily for resurfacing work including bridge repairs.
HARDIN COUNTY
SR128 from US64 (SR15) to near Clifton Road – There will be lane closures daily for resurfacing work including bridge repairs.
HAYWOOD COUNTY
SR180 Near Jeffries Road to Raymond Akin Road – Closed to through traffic
SR180 is closed to through traffic for crews to repair the bridge over Lost Creek just north of Nutbush, TN due to damage caused by the recent multi-day flood event.
HAYWOOD COUNTY
SR222 from near proposed SR468 to near Camp Ground Road
The reconstruction and widening of SR222 from near proposed SR468 to near Camp Ground Rd. will cause traffic disruption daily. Please use caution through the area.
HAYWOOD COUNTY
I-40 MM 49.2-51.0 at the Haywood County Weight Scales
July 7 and July 8, 7PM-6AM – Haywood County I-40 both east and westbound at the Haywood County weight scales there will be intermittent lane closures for crews to install “Pre-Pass” antennas and cameras.
HENDERSON COUNTY
I-40 from S.R. 104 (Exit 101) to S.R. 22 (Exit 108) The resurfacing on I-40 from near S.R. 104 to west of S.R. 22.
Restrictions – Speed limit is reduced from 70 MPH to 60 MPH on I-40.
Monday, July 7 through Wednesday, July 9, 7PM-6AM – There will be intermittent lane closures on I-40 east and westbound in Henderson County from MM101-MM108 for milling and paving operations.
LOOK AHEAD
Wednesday, July 9 through Wednesday, July 16, 7PM-6AM – There will be intermittent lane closures on I-40 east and westbound in Henderson County from MM101-MM108 for milling and paving operations.
HENDERSON COUNTY
S.R. 22 from Chester County line to Taylor Bailey Road – The resurfacing on S.R. 22 from the Chester County line (L.M. 0.00) to near Taylor Bailey Road (L.M. 8.98), including thin epoxy overlay on the bridge over Piney Creek will cause temporary lane closures in both directions. One lane will remain open at all times.
HENDERSON COUNTY
U.S. 412 (S.R. 20) from Madison County line to Crucifer Road – The resurfacing and miscellaneous safety improvements on U.S. 412 (S.R. 20) from the Madison County line (L.M. 0.00) to Crucifer Road (L.M. 4.33) will cause temporary lane closures in both directions. One lane will remain open at all times.
MADISON COUNTY
I-40 – Lower Brownsville Road to South Fork Forked Deer River – The resurfacing on I-40 from near Lower Brownsville Road to the South Fork Forked Deer River, including thin epoxy overlay will cause temporary lane closures in both directions. One lane will remain open at all times.
Restrictions – Speed limit is reduced from 70 MPH to 60 MPH on I-40.
Monday, July 7 through Wednesday, July 9, 7PM-6AM – There will be intermittent lane closures on I-40 east and westbound in Madison County from MM74-MM78 for milling and paving operations.
LOOK AHEAD
Wednesday, July 9 through Wednesday, July 16, 7PM-6AM – There will be intermittent lane closures on I-40 east and westbound in Madison County from MM74-MM78 for milling and paving operations.
MADISON COUNTY
I-40 at S.R. 138 (EXIT 68) The interchange improvements on I-40 at S.R. 138 (Exit 68) (L.M. 0.78 – L.M. 1.34), including grading, drainage, and paving will cause temporary lane closures in both directions. One lane will remain open at all times.
Restrictions: Speed limit is reduced from 70 MPH to 60 MPH on I-40.
Monday, July 7 through Wednesday, July 9, 7PM-6AM – There are no scheduled closures.
MADISON COUNTY
US412 (SR20) at Old Bells Road
There are inside lane closures both east and westbound at the intersection of US412 (SR20) and Old Bells Rd. *Old Bells Rd. Is also closed from US412 (SR20) to Bells Hwy. A Detour is posted.
District 49
FAYETTE COUNTY
SR-222 including the I-40 interchange (Exit 42) Grading, drainage, signals, and paving on SR 222 from Hebron Drive to near Thorpe Drive, including the I-40 interchange (Exit 42), will cause temporary lane closures in both directions. One lane will remain open at all times.
Restrictions – Speed limit is reduced from 45 MPH to 40 MPH on S.R.222.
Monday, July 7 through Wednesday, July 9, 8PM-4:30AM – There are no scheduled closures.
LAUDERDALE COUNTY
SR-19 from US51(SR3) to the Haywood County line – There will be intermittent temporary lane closures controlled by Flagging operations along SR 19 for geotechnical exploration.
SHELBY COUNTY
SR-57 (E. Poplar Avenue) from Fletcher Road to I-269 (SR-385)
Monday, July 7th at 6 a.m. to Sunday, July 20 – There will be intermittent temporary lane closures along Eastbound and Westbound SR-57 for roadway widening activities. Flaggers will be present for directing traffic. At least one lane will remain open at all times. Excluding Thursday, July 3rd at Noon until Monday, July 7th at 6 a.m., for Independence Day.
SHELBY COUNTY
Look Ahead
Monday, July 7 through Friday, July 11, 7 p.m. to 6 a.m. – There will be intermittent temporary lane closures along Eastbound and Westbound I-40 for shoulder gravel placement. At least one lane will remain open at all times.
SHELBY COUNTY
SR-23 (Walnut Grove Road) from SR-57 (Poplar Avenue) To I-240.
Nightly 7 p.m. – 6 a.m. – There will be nighttime lane closures along east and westbound Walnut Grove Road (SR-23) from Poplar Avenue (SR-57) to I-240 for pavement marking activities. One lane will remain open in both directions at all times.
Daily 9 a.m. – 3 p.m. – There will be daytime lane closures along east and westbound Walnut Grove Road (SR-23) from Poplar Avenue (SR-57) to I-240 for pavement marking activities. One lane will remain open in both directions at all times.
SHELBY COUNTY
SR-1 (U.S. 51) Danny Thomas Boulevard from Poplar Avenue (L.M. 2.85) to Jackson Avenue (L.M. 3.47), Daily, 9 a.m. – 3 p.m. – There will be temporary lane closures for ADA ramp construction and Traffic Signal installations. One or more lanes will remain open in both directions on (U.S. 51) Danny Thomas Boulevard at all times.
TIPTON COUNTY
US-51 (SR-3) from East Woodlawn Avenue to Winn Street – There will be temporary inside and outside lane closures on north and southbound US 51 from East Woodlawn Avenue to Winn Street DAILY to perform bridge repairs and resurfacing work. At least one lane in each direction will be open at all times.