The Tennessee Department of Transportation will halt all lane-closure activity on interstates and state highways for the Labor Day Weekend travel period. Construction crews will stop all lane-closure activity beginning at noon on Friday, September 4, and ending at 6:00 a.m. on Tuesday, September 8.
There may be DAYTIME or NIGHTTIME lane closures at various locations in Region 4 to make repairs or perform new installations on an as-needed basis throughout the 21 counties.
District 47
BENTON, CARROLL, HENRY, GIBSON, OBION, WEAKLEY, DYER COUNTY
VARIOUS ROUTES – Pavement markings will be repainted across the Region (West Tennessee). This will result in a slow-moving work zone on interstate and state routes in Shelby, Fayette, Haywood, Madison, Henderson, and Dyer counties.
VARIOUS ROUTES – Pavement testing will cause temporary lane closures in District 47.
BENTON COUNTY
I-40 at Exit 126 The grading, drainage, and paving on I-40 at the US-641 (SR-69) interchange (Exit 126) will cause temporary lane closures throughout the project.
BENTON COUNTY
SR-1 (US70) The grading, drainage, and paving on SR-1 (US 70) from the Camden Bypass to the Tennessee River will cause temporary lane closures throughout the project. The following roads are closed for construction. Traffic to utilize Cutt-Off Rd to access US-70 (SR-1):Â Missionary Grove Church Rd from US 70 (SR-1) to Old Hwy 70 and Old Hwy 70 from Missionary Grove Church Rd to US 70 (SR-1).
CARROLL COUNTY
SR-22 & SR-364 The Resurfacing on SR-22 from near SR77 to SR77 and SR364 from SR22 to SR77 will cause lane closures throughout the project paving and bridge repair.
CARROLL COUNTY
SR-76 (US-79) The grading, drainage, noise walls, signals, and paving on U.S. 79 (S.R. 76) from near S.R. 77 to near Cutlip Lane will cause lane closures throughout the project.
Meadowbrook Lane is closed.
Cutlip Lane Traffic was shifted to the new alignment from near Cutlip Ln. to the Connector Rd. leading into Trezevant, speed limit reduced to 35 MPH. Traffic will proceed down the new alignment to an All-Way Stop, then onto Old US79 (SR76).
Dorsey Rd is closed for utility realignment and road construction, weather permitting. The detour route is posted.
Clay Farm Rd is closed for utility realignment and road construction, weather permitting. The detour route along Newsome Rd. is posted.
Power Station Rd is closed for road construction, and traffic is detoured along US-70A/SR105 Main Street.
SR-105 Traffic is shifted to the new realignment close to Power Station Road.
DYER COUNTY
US-51 (SR-3) The Resurfacing on US-51 (SR-3) from near SR-181 to SR-78 will cause lane closures throughout the project for paving.
DYER COUNTY
SR-211 The Construction of a multimodal path along S.R. 211 from Samaria Bend Road to Horner Road will cause lane closures throughout the project.
DYER COUNTY
SR-211 The construction of a concrete Bulb-Tee beam bridge on SR-211 over overflow and over the North Fork Forked Deer River (just south of Dyersburg) including grading, drainage, and paving will cause the bridges to be closed.
DYER COUNTY
US-412 and US-51 INTERCHANGE The full-depth repair of the concrete ramp from SR-211 North/St. Johns Ave to US-412E (SR20), will cause the ramp to be closed. A signed detour will be provided.
DYER COUNTY
US-412 and I-155 INTERCHANGE The full-depth repair of the concrete ramp from US-412E (SR20) to I-155, will cause the ramp to be closed. A signed detour will be provided.
GIBSON COUNTY
SR-5 The miscellaneous safety improvements on U.S.45(SR-5) at the intersection of Broad Street in Dyer will cause lane closures throughout the project.
GIBSON COUNTY
SR-43 The repair of pipes by the City of Milan on US-45E (SR-43/N. 1st Street) from the intersection of US-79 (SR-76) to W. Woodrow Street will result in daily lane closures, one lane in each direction will be maintained.
GIBSON COUNTY
SR-105 The resurfacing on SR-105 from Shiloh Road to Wayne Lloyd Road will cause lane closures throughout the project for paving.
OBION COUNTY
SR-5 The resurfacing on US-45W (SR-5) from the Gibson County Line to Polk Station Road will cause lane closures throughout the project for paving.
OBION COUNTY
SR-43 The resurfacing on US-45E (SR-43) from the Weakley County Line to Kentucky State Line will cause lane closures throughout the project for paving.
HENRY COUNTY
SR-218 The Resurfacing on SR-218 from SR-77 to SR-76 will cause lane closures throughout the project for paving.
HENRY COUNTY
SR-54 The grading, drainage, construction of bridges, and paving on SR-54 from near Howard Road to the Kentucky State line cause lane closures throughout the project.
WEAKLEY COUNTY
SR-54 The Resurfacing on SR-2 from Cain Creek to SR-22 will cause lane closures throughout the project for paving.
District 48
CHESTER, CROCKETT, DECATUR, HARDEMAN, HARDIN, HAYWOOD, HENDERSON, MADISON, MCNAIRY
CHESTER COUNTY
SR100 between E. Main Street and Baker Road
Crews are replacing 2 bridges on SR100 between E. Main St. and Baker Rd. Â Construction of the bridges is complete. There may be intermittent lane closures to finish overall construction.
CHESTER COUNTY
Talley Store Rd. (County Road) is closed between Terry Lane past Talley Road
Talley Store Rd. closed for a bridge replacement.
CHESTER COUNTY
SR100 Intersection at SR-225
The construction of turn lanes at the intersection of SR100 and SR225 will cause temporary lane closures with flagging operations.
CROCKETT COUNTY
SR88 in Bells, TN in relation to relocating SR76 around Pictsweet
The following roads closed in Bells, TN
·        Central Ave. (SR88) from High St. To Christian Ave Ext.
·        Central Ave. (SR88), west of the CSX Railroad
·        Weddle St., south of Mitchell Ave.
·        Hicks St., from High St. to south of existing Central Ave. (SR88)
A posted detour will be in place for SR88.
HARDEMAN COUNTY
SR100 from near SR18 to near Firetower Road
The resurfacing on SR100 from near SR18 to near Firetower Road will cause temporary lane closures in both directions. One lane will remain open at all times. Motorists should watch for crew and equipment in the roadway.
HARDEMAN COUNTY
SR138 between SR100 and the Madison County line (LM 3.27- LM 9.58)
Monday, August 31 through Thursday, September 3, 8 a.m.-3:30 p.m. – SR138 in Hardeman county will have temporary intermittent full closures between SR100 and the Madison County line for cross drain replacements. A detour will be posted and message boards with adequate warning of the closures.
HARDEMAN COUNTY
SR125 between SR18 and the Chester County line (LM 19.73- LM 30.96)
Monday, September 14 through Friday, September 18, 8 a.m.-3:30 p.m. SR125 in Hardeman county will have temporary intermittent full closures between SR18 and the Chester County line for cross drain replacements. A detour will be posted and message boards with adequate warning of the closures.
HARDIN COUNTY
Bridge on SR 128 over the Pickwick Dam
Continuing through Wednesday, September 2 – There are no scheduled closures.
HARDIN COUNTY
SR 203 from Burnt Church Road to near Lonesome Pine Road
Resurfacing on SR203, from Burnt Church Rd. to Lonesome Pine Rd., will cause temporary lane closures. Motorists should watch for equipment entering the highway.
HARDIN COUNTY
S.R.69 from S.R. 15 to Sycamore Drive
The resurfacing work will cause daily lane closures.
HARDIN COUNTY
S.R. 142 from the McNairy County Line to S.R.57
The resurfacing work will cause daily lane closures.
HAYWOOD COUNTY
SR180 Near Jeffries Road to Raymond Akin Road – closed to through traffic
SR180 is closed to through traffic for bridge construction.
HAYWOOD COUNTY
SR19 from near Edward Grove Road to Jim Binford Lane
Coring operations on SR19, from Edward Grove Rd. To Jim Binford Ln., will cause temporary lane closures with flagging operations from September 2-9.
HAYWOOD COUNTY
I-40 Westbound from MM 56 to MM 52.5
Continuing through Friday, August 28, 8 p.m.-6 a.m. – There will be nightly lane closures on I-40 in Haywood County westbound between MM 56 to MM 52.5 to attach ITS Conduit under the bridges.
HENDERSON COUNTY
I-40 (Exit 101) at the SR104 Interchange
Continuing through Wednesday, September 2, 7PM-6AM – There will be nightly lane closures on I-40 east and west bound between MM100-102, including possible ramp closures at Exit 101 for ramp improvements including grading, drainage, lighting, and paving.
LOOK AHEAD
Wednesday, September 2 and Thursday, September 3, 7PM-6AM –Â There will be nightly lane closures on I-40 east and west bound between MM100-102, including possible ramp closures at Exit 101 for ramp improvements including grading, drainage, lighting, and paving.
Tuesday, September 8 and Wednesday, September 9, 7PM-6AM – There will be nightly lane closures on I-40 east and west bound between MM100-102, including possible ramp closures at Exit 101 for ramp improvements including grading, drainage, lighting, and paving.
MCNAIRY COUNTY
SR142 From US45 (SR5) to near Albert Robinson Road
The resurfacing will cause temporary lane closures. Motorists should watch for equipment entering the highway.
MCNAIRY AND CHESTER COUNTY
SR 224 from US64 to SR22A in Chester County
The resurfacing with cold in-place recycling (thin mix overlay) on SR224 from US 64 (SR15) in McNairy County to SR22A in Chester County, including bridge repair work will cause daily lane closures.
MCNAIRY COUNTY
SR 5 (US 45) from SR57 to US64
The resurfacing with cold in-place recycling on US45 (SR5) from SR57 to US 64 (SR15), including concrete repair on the bridge over Roland Creek will cause daily lane closures.
District 49
SHELBY, FAYETTE, TIPTON, LAUDERDALE COUNTY
INTERSTATE
SHELBY COUNTY
I-40 Eastbound from Levee Rd. to Hollywood Street (L.M. 4.65 to L.M. 7.50)
There will be long-term lane closures on East and Westbound I-40 inside lanes for rubblization and paving operations. At least two lanes in the east and westbound direction will remain open at all times.
·         Hollywood St. Eastbound and Westbound entrance ramps: The entrance ramps from Hollywood St to East and Westbound I-40 will be closed with a posted detour in place.
Nightly, 9 p.m. to 6 a.m. – There will be intermittent temporary lane closures for paving operations. One lane will remain open in each direction at all times.
WEATHER PERMITTING
SHELBY COUNTY
I-40 from near Sycamore View Road to Fletcher Creek
Nightly, 8 p.m. to 6 a.m.
·        There will be intermittent nightly lane closures on East and Westbound I-40 for paving operations. One lane will remain open in both directions at all times.
SHELBY COUNTY
I-40 Eastbound Bridge over Chester Street (L.M. 29.6 to L.M. 30.0)
Nightly, 8 p.m. to 6 a.m. – There will be intermittent lane closures on east and westbound I-40 from MM 26.0 to MM 26.4 to perform bridge repairs. At least one lane in each direction will remain open at all times.
Chester Street at I-40
North and Southbound Chester Street will be closed from Larry Anderson Lane to Scarlet Ridge Drive to perform bridge repairs on the I-40 bridges at L.M. 29.8. Chester street will remain closed for the duration of the project.
SHELBY COUNTY
SR- 14/ US-61 (Third Street) Bridges over ICRR and Nonconnah Creek (L.M. 7.13) Shelby County, Tennessee. Interstate 55 Exit Ramp Bridge to State Route 14 (L.M. 7.44) State Route 14 (South 3rd Street) Bridge over Interstate 55 (L.M. 7.46)
The following ramps on US-61 S Third St (SR14) at I 55 will continue to remain closed with detours in place:
·         Northbound S.R. 14 to northbound I-55.
·         Southbound S.R. 14 to southbound I-55.
·         Southbound I-55 to southbound SR-14
·         Northbound I-55 to northbound/southbound SR-14
Northbound SR-14 traffic was reduced to one lane from the approach to the bridge over Nonconnah Creek to just beyond the northbound SR-14 to northbound I-55 loop ramp. Drivers can expect intermittent flagging on SR14.
Continuing through Friday, August 28, 8 p.m. to 6 a.m. – There will be intermittent lane closures on northbound and southbound I-55 and northbound and southbound SR-14.
* As of August 12, 2026, the Third Street Bridge over I-55 is temporarily CLOSED.
SHELBY COUNTY
I-55 from near Mill Branch to I-240
Nightly, 8 p.m. to 6 a.m. – There will be intermittent lane closures for bridge repair and paving operations. One lane to remain open in both directions at all times.
SHELBY COUNTY
I-240 from I-40 to I-55
Nightly, 8 p.m. to 6 a.m. – There will be intermittent lane closures for resurfacing operations. One lane to remain open in both directions at all times.
SHELBY COUNTY
I-240 from near Elvis Presley Blvd to near S Perkins Road
Nightly, 8 p.m. to 6 a.m. – There will be intermittent lane closures for resurfacing operations. One lane to remain open in both directions at all times.
I-240 East from SR-4 (Lamar Ave.) and Getwell Road
Friday, August 28, 8 p.m. through Monday, August 31, 6 a.m. – There will be temporary lane closures along I-240 East for bridge repair activities on the Black Bayou Bridge. At least one lane will remain open at all times. Exit 20A-B (Getwell Road) from I-240 East will be temporarily closed. WEATHER PERMITTING
*September 11 through the 14 will serve as backup dates
SHELBY COUNTY
I-240 from near S. Perkins to near Park Avenue
Nightly, 8 p.m. to 6 a.m. – There will be intermittent lane closures for resurfacing operations. One lane will remain open in both directions at all times.
Friday, August 28, 8 p.m. to Monday, August 31, 6 a.m.
SR385 Westbound to I-240 East towards Nashville will be closed for concrete pavement repairs. Detour(s) will be posted.
FAYETTE COUNTY
I-269 (SR-385) from near SR-86 (U.S. 72) to SR-193 (Macon Road)
Nightly, 8 p.m. to 6 a.m. – There will be intermittent lane closures for resurfacing operations. At least one lane will remain open in both directions at all times.
STATE ROUTES
FAYETTE COUNTY
SR-15 (U.S. 64) from near Tomlin Road to near Woodbridge Road
Daily – There will be temporary lane closures on east and westbound SR-15 from near Tomlin Road to near Woodbridge Road to perform resurfacing work. At least one lane in each direction will remain open at all times.
SHELBY COUNTY
SR-1 (N. Parkway) from near Danny Thomas Street to Tillman Street
Nightly from 8 pm to 6:00 am – There will be intermittent temporary lane closures for resurfacing operations. At least one lane in each direction is to remain open at all times.
SHELBY COUNTY
SR-1 (U.S. 70, Summer Ave.) from near I-40 to North of Sycamore View Road
Daily – There will be temporary lane closures along Westbound and Eastbound SR-1 for roadway widening activities. Eastbound SR-1 will be reduced from two lanes to one lane beginning at the I-40 Frontage Road and ending East of Sycamore View Road. Westbound SR-1 will be reduced from two lanes to one lane beginning near Munson Road and ending at the I-40 Frontage Road. Trucks will be entering and exiting the work zone along SR-1. Flaggers will be present for directing traffic as necessary. At least one lane in each direction will remain open at all times.
Access to Summer Trees Drive along SR-1 (Summer Avenue) will be temporarily closed with detours in place.
SHELBY COUNTY
SR-3 (US51 Thomas St.) from Near Wolf River and Levee Road to Stage Road
Daily – There will be a long-term lane closure, Northbound and Southbound traffic will be reduced to 1 lane in each direction with a traffic shift in place to begin bridge replacement. At least one lane in each direction to remain open at all times.
SHELBY COUNTY
SR-4 from South of Shelby Drive to the Raines/Perkins Road interchange – The following routes will be affected due to roadway widening activities along SR-4.
Affected Routes:
·         Lamar Avenue (SR-4) Speed limit reduced from 55 mph to 45 mph from South of Shelby Drive to the Raines/Perkins Road interchange
·         Shelby Drive (SR-175) Speed limit reduced from 45 mph to 35 mph at the intersection with Lamar Avenue (SR-4)
·         Pleasant Run Road Closed to thru traffic from Pleasant Hill Road. Pleasant Run Road is closed from Lamar Avenue (SR-4)
SHELBY COUNTY
SR-14 from Kerrville Rosemark Road to the Tipton County line
The widening on SR-14 (Austin Peay Highway) from Kerrville-Rosemark to the Tipton County line will cause shoulder closures and temporary lane closures in both directions. There will be intermittent lane closures daily on eastbound and westbound SR 14 to perform grading, drainage, and paving work. Tracy Rd., Idaville Rd., Mulberry Rd., and Gragg Rd. will be closed, and a detour put in place.
SHELBY COUNTY
SR-57 (E. Poplar Avenue) from Fletcher Road to I-269 (SR-385)
Daily – There will be intermittent temporary lane closures along East and Westbound SR-57 for roadway widening activities. Flaggers will be present for directing traffic. At least one lane will remain open at all times.
TIPTON COUNTY
SR-3 from North Myron Creek to South of Old Highway 51
The southbound outside and northbound inside lanes will be closed to begin turn lane construction for the Tipton County landfill
Shelby County
LOOK AHEAD
S Collierville Arlington Road (Old SR 205) from Shelton Drive to Raleigh Lagrange Road
Beginning September 8- Â The bridge over the Wolf River on S Collierville Arlington Road in Collierville will be closed from Shelton Drive to Raleigh Lagrange Road with a detour in place for bridge reconstruction.
TIPTON COUNTY
SR-179 from SR-54 to SR-14 – There will be temporary lane closures on east and westbound SR 179 from SR 54 to SR 14Â DAILYÂ to perform resurfacing work.