From the Department of Transportation –
MADISON COUNTY I-40: The grading, drainage, construction of bridges, retaining walls and noise walls, ITS and paving on I-40 from west of US 412 (SR 20, Hollywood Drive) to west of the US 45 Bypass (SR 186).
Continuing through Wednesday, February 1, 7 p.m. – 6 a.m. – (AS NEEDED):
I-40 east and westbound will have intermittent lane closures from east of MM 76.0 (Exit 76) to east of MM 80.0 for equipment mobilization and Phase II widening work.
Restrictions – There is an 11-foot width restriction east and westbound on I-40 from MM 76.9 to MM 82.3 with no shoulder. Speed limit is reduced to 65 MPH on I-40 eastbound from MM 75.2 to MM 76.9 and 55 MPH from MM 76.9 to MM 79.9. Speed limit is reduced to 55 MPH I-40 westbound from MM 82.3 to MM 78.4.
LOOK AHEAD: Wednesday, February 1 through Wednesday, February 8, 7 a.m. – 6: a.m. (AS NEEDED): I-40 east and westbound will have intermittent lane closures from east of MM 76.0 (Exit 76) to east of MM 80.0 for equipment mobilization and Phase II widening work.
MADISON COUNTY I-40: The grading, drainage and paving with Portland Cement Concrete on I-40 (Exit 93) at the SR 152 (Law Road) interchange.
Continuing through Wednesday, February 1, 7 p.m. – 6 a.m. – (AS NEEDED):
I-40 east and westbound from MM 92.0 to MM 94.0 will have intermittent left and right lane closures for construction activities.
LOOK AHEAD: Wednesday, February 1 through Wednesday, February 8, 7 a.m. – 6 a.m. (AS NEEDED): I-40 east and westbound from MM 92.0 to MM 94.0 will have intermittent left and right lane closures for construction activities.