Road construction schedule for Jackson-Madison County

From the Tennessee Department of Transportation –

MADISON COUNTY, I-40: The widening of I-40 east of US 45 (SR 5) MM 82.0 to east of US 70
(SR 1) MM 87.0 in Jackson, including bridges, retaining walls and installation of TDOT Smartway Intelligent Transportation System.

Continuing through Wednesday, September 21, 7 p.m. – 6 a.m. – I-40 east and westbound from MM 82.0 to MM 87.0 will have intermittent left and right lane closures for construction activities.

Restrictions: There is an 11-foot width restriction east and westbound from MM 82.1-MM 88.5. The speed limit is reduced to 55 MPH through the work zone.

LOOK AHEAD:

Wednesday, September 21 through Wednesday, September 28, 7 p.m. – 6 a.m. – I-40 east and westbound from MM 82.0 to MM 87.0 will have intermittent left and right lane closures for construction activities.

MADISON COUNTY, I-40: The grading, drainage, construction of bridges, retaining walls and noise walls, ITS and paving on I-40 from west of US 412 (SR 20, Hollywood Drive) to west of the US 45 Bypass (SR 186).

Wednesday, September 14 through Wednesday, September 21, 7 p.m. – 6 a.m. – I-40 east and westbound will have intermittent lane closures from east of MM 76.0 (Exit 76) to east of MM 80.0 for equipment mobilization and Phase II widening work.

LOOK AHEAD: Wednesday, September 21 through Wednesday, September 28, 7 p.m. – 6 a.m. – (AS NEEDED) I-40 east and westbound will have intermittent lane closures from east of MM 76.0 (Exit 76) to east of MM 80.0 for equipment mobilization and Phase II widening work.

MADISON COUNTY, SR-18: The resurfacing on SR 18 from near Meridian Creek to US 45 (SR 5) may cause possible daytime temporary lane closures. Motorist should watch for crews and equipment in the roadways.

Share On

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top
Monday-Friday
Saturday-Sunday

Deal Of the Day

Monday

MondayGet Deal

Crypto Brought To You By Mann's Wrecker

    Bitcoin