BlueOval City – timeline; by the numbers

Timeline

 

September 2021 – Ford and SK
On announce the creation of
BlueOval City, Ford’s largest,
most advanced auto production
complex ever

 

July 2022 – Ford breaks ground
at BlueOval City and installs the
first structural steel

 

July 2023 – Tennessee Electric
Vehicle Center structural steel
top-out

 

January 2024 – Tennessee
Electric Vehicle Center roofing
complete

 

April 2025 – Ford team moves
into Tennessee Electric Vehicle
Center

 

April 2025 – Tennessee Electric
Vehicle Center signage installed

 

May 2025 – Sculpture brings
symbols of West Tennessee
community to BlueOval City

 

By the Numbers

 

16 million cubic yards of soil
moved – enough to fill five Great
Pyramids of Giza

 

77,000 tons of structural steel
installed – equal to the weight
of eight Eiffel Towers

 

1.7 million tons of stone laid –
the weight of five Empire State
Buildings

 

2.1 million tons of concrete
poured – the weight of nine
large cruise ships

 

187 miles of pipe installed – the
distance from Stanton to
Nashville

 

96 miles of electrical power
distribution cable installed
45 miles of mechanical piping
installed

 

10.8 million square feet of
buildings – the size of 188
football fields

Share On

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top
Monday-Friday
Saturday-Sunday

Deal Of the Day

Brought To You By

Brought To You ByGet Deal

Stock Market Brought To You By Talk N West TN

Crypto Brought To You By Mann's Wrecker

    Bitcoin