TDOT Temporary Road Closures for SR-186 (US45 Bypass) I-40, & SR-5:
MADISON COUNTY, SR-186 (US 45 Bypass) and I-40: Interchange improvements on SR 186 (US 45) north and southbound from the I-40 ramps to Old Hickory Blvd for paving and construction of retaining walls. Widening of I-40 from just east of Exit 79 to just east of Exit 82.
Thursday, July 26, 9:00 a.m.-3:00 p.m.: SR186 (45 Bypass) will have lane closures to the right lanes both north and south bound at the I-40 bridge for the removal of temporary barrier rail. Weather Permitting. Backup Date will be Friday, July 27, 9:00 a.m.-3:00 p.m.
Saturday, July 28, 5:00 a.m.-5:00 p.m.: There will be intermittent single lane closures on I-40 westbound between MM 82-80 for median work. Weather Permitting.
Backup Date will be Sunday, July 29, 5:00 a.m.-5:00 p.m.
Monday, July 30 through Friday, August 3, 9:00 a.m.-5:00 p.m.: There will be intermittent single lane closures on SR186 (45 Bypass) southbound at the I-40 Bridge for paving at the bridge ends.
Monday, July 30 through Friday, August 3, 5:00 a.m.-3:00 p.m.: There will be intermittent single lane closures on SR186 (45 Bypass) northbound at the I-40 Bridge for paving at the bridge ends.