From the Tennessee Department of Transportation –
Madison County – I-40 –The grading, drainage, construction of bridges, retaining walls and noise walls, ITS and paving on I 40 from west of US 412 (SR 20, Hollywood Drive) to west of the US 45 Bypass (SR 186).
Continuing through Wednesday, August 9, 7 p.m. – 6 a.m. – There are no scheduled closures.
LOOK AHEAD –
Monday, August 14, 6 p.m. – 6 a.m. – SR 20 (US 412/Hollywood) will have intermittent lane closures and the use of crossovers going east and westbound from north of the Exit 79 interchange to south of the Exit 79 interchange for the WB deck pour on the SR 20 Bridge.
Madison County, I-40 –The grading, drainage and paving with Portland Cement Concrete on I 40 (Exit 93) at the SR 152 (Law Road) interchange.
Continuing through Wednesday, August 9, 7 a.m. – 6 p.m. – I-40 eastbound will have intermittent lane closures from MM 92.0 to MM 94.0 for construction activities.
LOOK AHEAD –
Wednesday, August 9 through Wednesday, August 16, 7 a.m. – 6 p.m. (AS NEEDED) – I-40 east and westbound will have intermittent lane closures from MM 92.0 to
MM 94.0 for construction activities.
Madison County SR-20
LOOK AHEAD: Monday, August 14 and Tuesday, August 15, 7 a.m. – 5 p.m. – There will possible lane closures from SR 1 to Liberty-Claybrook Road to perform coring work.