YOU'RE LISTENING TO

Red Eye Radio

12:00 am - 5:00 am

YOU'RE LISTENING TO

Red Eye Radio

12:00 am - 5:00 am

Road work schedule for Jackson-Madison County

From the Tennessee Department of Transportation –

MADISON COUNTY, SR 5 (US 45) (NON-TDOT)

Thursday, November 21, 8 a.m. – 11 a.m. – There will be lane closures on SR 5 (US 45) at
the Forked Deer River Bridge south of Three-Way north and southbound to perform a deck sounding. One lane to remain open.

MADISON COUNTY, SR-186 (US 45 Bypass) and I-40: Interchange improvements on SR 186 (US 45) north and southbound from the I-40 ramps to Old Hickory Blvd for paving and construction of retaining walls. Widening of I-40 from just east of Exit 79 to just east of Exit 82.

Thursday, November 21 and Friday, November 22, EACH DAY, 9 a.m. – 3 p.m. – SR 5 (Highland Avenue) will have intermittent left and right lane closures both north and southbound from Vann Drive to the Carriage House/Ridgecrest intersection for bridge construction activities.

Saturday, November 23, 3 a.m. – 8 p.m. – I-40 east and westbound at Exit 82 will be closed and detoured onto the Exit 82 ramps. Highland Avenue (SR 5) will be closed at the interchange to allow for continuous flow of interstate traffic. This closure is to allow for Phase 1 deck pour.
*Back up date Sunday, November 24, 3 a.m. – 8 p.m.

Monday, November 25 through Tuesday, November 26, EACH DAY, 9 a.m. – 3 p.m. AND Wednesday, November 27, 9 a.m. – 3 p.m.: SR 5 (Highland Avenue) will have intermittent left and right lane closures both north and southbound from Vann Drive to the Carriage House/Ridgecrest intersection for bridge construction activities.

LOOK AHEAD

Monday, December 2 through Wednesday, December 4, EACH DAY, 9 a.m. – 3 p.m. –
SR 5 (Highland Avenue) will have intermittent left and right lane closures both north and southbound from Vann Drive to the Carriage House/Ridgecrest intersection for bridge construction activities.

Backup Date – Saturday, December 7 and Sunday, December 8, 4 a.m. – 8 p.m. – I-40 east and westbound at Exit 82 will be closed and detoured onto the Exit 82 ramps. Highland Avenue (SR 5) will be closed at the interchange to allow for continuous flow of interstate traffic. This closure is to allow for Phase 1 deck pour.

Share On

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top
Monday-Friday
Saturday-Sunday

Deal Of the Day

Monday

MondayGet Deal

Stock Market Brought To You By Talk N West TN

Crypto Brought To You By Mann's Wrecker

    Bitcoin