Road work schedule – Jackson-Madison County

From the Tennessee Department of Transportation –

Madison County – I-40 – The grading, drainage, construction of bridges, retaining walls and noise walls, ITS and paving on I 40 from west of US 412 (SR 20, Hollywood Drive) to west of the US 45 Bypass (SR 186).

Continuing through Tuesday, September 5: There are no scheduled closures.

LOOK AHEAD:

Wednesday, September 6 and Thursday, September 7, 7 p.m. – 6 a.m. – I-40 eastbound will have right lane closures from east of MM 76.0 (Exit 76) to east of MM 80.0 for removal/installation of portable barrier rail.

Madison County – I-40 – The grading, drainage and paving with Portland Cement Concrete on I 40 (Exit 93) at the SR 152 (Law Road) interchange.

Thursday, August 31, 7 p.m. – 6 a.m. – I-40 east and westbound from MM 92.0 to MM 94.0 will have intermittent left and right lane closures for construction activities.

Tuesday, September 5 and Wednesday, September 6, 7 p.m. – 6 a.m. – I-40 east and westbound from MM 92.0 to MM 94.0 will have intermittent left and right lane closures for construction activities.

LOOK AHEAD –

Wednesday, September 6 through Wednesday, September 13, 7 p.m. – 6 a.m. – I-40 east and westbound from MM 92.0 to MM 94.0 will have intermittent left and right lane closures for construction activities. All lanes will open by 6AM.

Madison County – The resurfacing on US 70 (SR 1) from near Mobile Street to Whitehall Street will cause temporary lane closures in both directions. One lane will remain open at all times. Motorists should watch for crews and equipment in the roadways.

Share On

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top
Monday-Friday
Saturday-Sunday

Deal Of the Day

Stock Market Brought To You By Talk N West TN

Crypto Brought To You By Mann's Wrecker

    Bitcoin