MADISON COUNTY, SR-186 (US 45 Bypass) and I-40: Interchange improvements on SR 186 (US 45) north and southbound from the I-40 ramps to Old Hickory Blvd for paving and construction of retaining walls. Widening of I-40 from just east of Exit 79 to just east of Exit 82.
LOOK AHEAD
Thursday, August 1 8:00 pm – 6:00 am
I-40 EB and WB plus Exit 82 ramps will have intermittent closures for paving operations
Highland Avenue will have intermittent lane closures between Carriage House Drive and Vann Drive for paving operations
Thursday, August 1 – Friday, August 2, EACH DAY from 9:00 am – 3:00 pm
Highland Avenue will have intermittent lane closures between Carriage House Drive and Vann Drive for construction activities
Friday, August 2, 8:00 pm – Monday, August 5, 6:00 am *BACK UP DATES
I-40 EB will have intermittent lane closures between mile markers 80-82 for milling and paving operations I-40, Exit 80 ramps will have intermittent closures for paving operations